Hwy 123 Sandstone

Pine County

Project complete

Project purpose

A rendering of the Hwy 123 Sandstone project.

Click image for full-size image

Urban section (Hwy 23 to Kettle River Bridge)

  • Roadway resurfacing
    • Between Hwy 23 and Division Street will be a reclaim (with 2” mill) and overlay
    • Between Division Street and Park Avenue will be a 2” mill and overlay
  • Realignment of Hwy 123 and Hwy 23 intersection.
  • Pedestrian curb ramps will be updated to meet current ADA standards
  • Extend sidewalk along Main Street from Phase Recycling to Old Military Road
  • Extend sidewalk along 3rd street on north side of the road from Court Avenue to Park Avenue and widen shoulder from Park Avenue to Grand Avenue to accommodate a walkable/bikeable connection
  • Storm sewer and drainage improvements
  • Isolated sidewalk and curb and gutter replacement (on in-place system)

Rural section (Park Avenue to Hwy 30)

  • Roadway section will consist of a full depth bituminous reclaim and overlay
  • Addition of a right turn lane at Prison Road

Public meetings

Past public meeting

April 27, 2022

Thursday, Oct. 1, 2020