Hwy 25 roundabout—north of Hwy 55
Wright County project
Construct a roundabout at Hwy 25 and Co. Rd. 83/138 in Buffalo (35th St. NE) in 2024. The estimated $1.7 million project includes pedestrian walks and approaches. Visit the Wright County website for more details.
Future impacts
The intersection will close at Hwy 25 and Co. Rd. 83/138 in Buffalo.
Reconstruct Hwy 25 from First St. S to the curve north of Settlers Pkwy. in 2023-2024. The $10.8 million project includes updates to city utilities, pedestrian sidewalks and approaches. Visit the city of Buffalo website for more details.
Impacts, schedule
Work operations suspended for the 2023–2024 winter season. Off-road work to occur along the entire project year-round. The city plans to get an early start in April, since the winter season has been warmer than usual.
Construct April 1 to late summer 2024: The city will close Hwy 25 between Co. Rd. 12 and Settlers Pkwy. April 1 through mid-June. Any remaining work will be completed under traffic by late summer.
Hwy 25 detour: Co. Rd. 12 and Hwy 12 at Montrose. Local traffic to use Settlers Pkwy, Hwy 55 and Second St. S
Construct 2023: Complete
Summary of work
Reconstruct Hwy 25 from First St. S to north of Settlers Pkwy.
Install a continuous center left turn lane to improve access
Replace underground utilities—water main, sanitary sewer and storm sewer
Install sidewalk (8 ft. wide) along the east side of Hwy 25 south of Montrose Blvd. and along the west side north of Montrose Blvd.
Install bicycle lane and shoulder (6 ft. wide) along both sides of Hwy 25 south of Second St. S
Remove parking along both sides, except on the west side of Sturges Park, to expand the community commons area and open space along Buffalo lake between First St. S and Second St. S