Mid-April to mid-October 2025

Here's a six-month look ahead on tentative roadwork and traveler impacts on Hwy 55 between Annandale Blvd. and Brown Ave. in Annandale, Wright County.

Schedule at a glance

Table figure: provides project timeframe, location, work and expected impacts on Hwy 55.

Timeframe
Location
Work
Hwy 55 impacts

Complete

Annandale Blvd. to Poplar Ave.

Prep-work east to west: widen shoulders along south side of Hwy 55 for future traffic lanes, set up equipment, road devices, etc.

Minimal impacts, shoulder closures

April 29 to October

Annandale Blvd. to Poplar Ave.

East to west: widen road along north side, pave, add center turn lane

Narrow lanes, two-way traffic with no shoulders

May 6 to mid-October

Brown Ave. to Poplar Ave.

West to east: reconstruct road, sidewalks, replace signals, improve access

Road closed to through traffic. Detour: Wright Co. Rd. 3, County Rd. 39, Hwy 24 and Co. Rd. 6 (PNG)

October

Annandale Blvd. to Brown Ave.

Wrap up: Complete any remaining work, remove equipment and traffic control devices

Periodic shoulder or lane closures; mainly off-road work

Information subject to change - weather, contractor schedules and material delays can occur.