Minnesota Department of Transportation

511 Travel Info

I-94

Minneapolis

This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.

Traffic impacts

-94 between East River Pkwy./Franklin Ave. and just west of Hwy 55/Hiawatha Ave./I-35W project area map.

I-94 in Minneapolis project area map

View full-size map

All traffic impacts are tentative and weather dependent.

Current

Lane closures

5 a.m. Mon, April 7 through mid-August
  • I-94 is reduced to two lanes in both directions between 11th Ave. South and Franklin Ave. Southeast
5 a.m. Mon, March 31 through 5 a.m. Mon, June 16
  • The following ramps are reduced to one lane:
    • Southbound I-35W to eastbound Hwy 55
    • Westbound Hwy 55 to westbound I-94
    • Westbound Hwy 55 to South 7th St.

Ramp closures

9 a.m. Fri, April 4 through 5 a.m. Mon, June 16
9 p.m. Fri, April 4 through mid-August

Upcoming

Information about upcoming traffic impacts will be posted as details become available. All lanes on I-94 between 11th Ave. South and Franklin Ave. Southeast are expected to reopen to traffic for the Minnesota State Fair from mid-August through Labor Day. Work will resume after Labor Day to complete the removal of crossovers and other items such as signage and lighting.

Road closures

10 p.m. Fri, June 13 through 5 a.m. Mon, June 16

Ramp closures

9 p.m. Fri, June 13 through late August
5 a.m. Mon, June 23 through Mon, June 30
  • The ramp from Hwy 55 to westbound I-94 is closed

Lane closures

5 a.m. Mon, June 16 through early August
  • Cedar Ave. is reduced to one lane in each direction under the I-94 bridges

Bridge closures

Mid-July through early August

About this project

We will be doing maintenance and repair work on five bridges along I-94 in Minneapolis. These bridges include:

  • I-94 bridge (Dartmouth Bridge) that spans the Mississippi River
  • Riverside Ave. bridge over I-94
  • I-94 over Cedar Ave.
  • I-94 over the Light Rail Transit (Blue Line)
  • I-94 over Hwy 55/Hiawatha Ave.

Summary of work

  • Construct temporary crossovers
  • Repair bridge decks
  • Resurface bridge pavement
  • Remove and replace bridge joints
  • Update guardrails
  • Upgrade drainage
  • Repaint bridge steel