About this 2026 project
MnDOT will improve access and safety at the north junction of Hwy 27 and Hwy 169 with a new roundabout. The project is in the detail plan phase and is scheduled for construction in 2026.
Summary of work
- Install a four-legged roundabout at the intersection of Hwy 27, Hwy 169 and the west Frontage Rd.
- Reconstruct adjacent entrances:
- Realign Co. Rd. 35 (Twilight Rd.) to/from westbound Hwy 27
- Install right in-out entrance at the Veterans Club on eastbound Hwy 27
- Install concrete median with 3/4 accesses to/from Hwy 169
- Install pedestrian crosswalks and approaches