There are six sites along I-90 in Austin that have bridges that are scheduled to be replaced or repaired 2024 to 2026. In a separate, earlier, project, a bridge at 11th Dr. NE was replaced in 2017 and a bridge at 28th St. NE was replaced in 2021.
Construction in 2024 started April 19 and it is anticipated to go through the fall.
Which bridges are part of this project?
There are six sites along I-90 in Austin involved in the project with each having different needs.
2024-2025
Oakland Ave. W / Hwy 105
A new bridge will be constructed at Oakland Ave. (Hwy 105) over I-90. Oakland Ave. will be closed during construction. The new bridge will include a wide walkway, which will connect to a future city/county trail. Construction started April 19, 2024 and will go through mid-October.View the design.
4th St. / Co. Rd. 45
A new interchange will be constructed to replace the current interchange. The new layout will provide for safer walkway crossings of I-90 and improved traffic flow. 4th St. will be closed for construction starting in the fall of 2024 and through the majority of the 2025 construction season. This construction is currently scheduled for 2024-2025. The demolition of the current bridge is scheduled to occur mid-October 2024, and construction of the new bridge is expected to be finished fall of 2025. View the design.
6th St. and Cedar River
Both I-90 bridges over 6th St. will be resurfaced and two new I-90 bridges over the Cedar River will be constructed. Work on the eastbound bridges started May 31 and will be finished in fall of 2024. The I-90 westbound bridge work over 6th St. and the Cedar River will occur in the 2025 construction season.
2026
14th St. / Hwy 218 North
The two bridges at this location will be replaced by one bridge and roundabouts will be constructed at each ramp intersection with 14th St. The southbound bridge will stay open to the extent possible during construction. Short duration detours will be provided at 4th St. This construction is currently scheduled for 2026. View the proposed design.
21st St. / Hwy 218 South
The 21st St. bridge and the south ramps will be reconstructed. The new bridge crossing will provide a wide walkway and connections to local trails. 21st St. will be closed during construction. 11th Dr. and 28th St. will be available for short detours. This construction is currently scheduled for 2026. View the proposed design.
Why are they being replaced?
I-90 is an important national east-west transportation route that connects many population centers in the U.S. in the Austin area. I-90 was built in the 1950s and the structures are at the end of their useful design life.
Traffic impacts
I-90 eastbound lanes are closedbetween Oakland Ave. and 11th Dr. NE.
I-90 traffic will be in the westbound lanes with eastbound and westbound traffic using single lanes adjacent to each other.
I-90 eastbound bridge resurfacing over 6th St.
Scheduled May 31 to fall 2024
I-90 eastbound off-ramp to 6th St. is closed and detoured:
I-90 eastbound motorists should use Exit 179 (11th Dr.), take a left and use the on-ramp to I-90 westbound. Next, motorists should take Exit 178B, the 6th St. exit.
I-90 eastbound on-ramp from 6th St. is closed and detoured:
Motorists should take the I-90 westbound on-ramp from 6th St., then take Exit 177 (Hwy 218 N/14th St. exit), take a left and use the I-90 eastbound on-ramp.
I-90 eastbound bridge construction over Cedar River
Scheduled June 3 to fall 2024
Cedar River closed: If you use boats, kayaks or canoes on the Cedar River in Austin, be alert that the river is closed until fall 2024.
Crews will be demolishing the eastbound bridge and removing the center pier. Once the removal work is done, it will continue to be dangerous to be on the water at this site, because construction crews will be building the new pier and abutments near or in the river channel.
During the I-90 bridge replacements, that section of the Cedar River State Water Trail will be off limits to paddlers and boaters who go through that part either from the upstream side or downstream where the city has a boat ramp on Austin Mill Pond.
For people using the new canoe/kayak access below Ramsey Dam (3 river miles upstream from I-90), a small, rock access is available on Wolf Creek in Austin's Wildwood Park to get off the river. Paddlers need to turn upstream at the V-shaped confluence just north of I-90 and paddle upstream about 100 yards. Road access is on 17th Ave. NE, about 200 feet east of the landing.
Oakland Ave. bridge
Scheduled April 19 to mid-October 2024
The Oakland Ave. bridge over I-90 is closed and detoured. Ramps will be open for the majority of the time.
Motorists traveling west on Oakland Ave. should use the on-ramp to I-90 eastbound, then take Exit 177 to Hwy 218, take a left over the bridge and use the on-ramp to I-90 westbound. Next, motorists should use Exit 175 to go west on Oakland Ave./Co. Rd. 46.
Motorists traveling east on Oakland Ave. should use the on-ramp to I-90 westbound, then take Exit 166 to Co. Rd. 46, take a left and use the on-ramp to I-90 eastbound. Next, motorists should use Exit 175 to go east on Oakland Ave.
There will be occasional ramp closures at Oakland Ave. Once the schedule is determined, the dates will be put on the website and communicated through the project update emails.
I-90 eastbound motorists will be detoured to Exit 175 (Hwy 218).
I-90 westbound motorists will be detoured to Exit 166 (Co. Rd. 46).
I-90 on and off-ramp detours at Hwy 105/Oakland Ave.
Scheduled Aug. 28 to mid-October 2024
Westbound motorists wanting to reach the north side of I-90 should travel west on I-90 and use exit 166 at Freeborn Co. Rd. 46, traveling east on Co. Rd. 46 back to their destination. Motorists on the north side of I-90 should use Co. Rd. 46 to reach I-90. Motorists who want to reach Hwy 105 should use exit 177 and travel south on 14th St. Northwest.
Eastbound motorists wanting to reach the north side of I-90 can exit at exit 166 and use Co. Rd. 46. Motorists who want to reach the south side of I-90 or Hwy 105 should travel east and use exit 177 and travel south on 14th St. Northwest to Hwy 105.
I-90 eastbound ramps at 4th St.
Scheduled May 2024 to fall 2024
I-90 eastbound off-ramp to 4th St. is closed and detoured:
I-90 eastbound motorists should use Exit 179 (11th Dr.), take a left and use the on-ramp to I-90 westbound. Next, motorists should take Exit 178A, the 4th St. exit.
I-90 eastbound on-ramp from 4th St. is closed and detoured:
Motorists should take the I-90 westbound on-ramp from 4th St., then take Exit 177 (Hwy 218 N/14th St. NW exit), take a left and use the I-90 eastbound on--ramp.
4th St. bridge closed
Scheduled mid-October to fall 2025
The demolition of the current bridge is scheduled to occur mid-October 2024, and construction of the new bridge is expected to be finished fall of 2025.
Detours will be in place.
It is anticipated that the ramps on the north side of the bridge will be closed until fall of 2025, the ramps on the south side will reopen once the I-90 Cedar River bridge reopens fall of 2024.