I-90 resurfacing, bridge replacement

Nodine to Dakota

About this project

Traffic impacts

  • I-90 lane closures lane closures will continue for the resurfacing work and will remain in place through late fall. 
  • I-90 eastbound on-ramp at Nodine from Winona County Road 12 will be detoured beginning May 11.
    • With the eastbound entrance ramp closed, the detour to enter eastbound I-90 is to go west on I-90 to Exit 257 (Highway 76, Houston), cross over and return to eastbound I-90. The detour is approximately 16 miles. Traffic will be detoured through June 19. The other three ramps will remain open.
  • Winona County Road 101 will be closed and detoured during the bridge replacement, which begins May 18. The county road detour is expected to be several months at a time as crews replace the bridge half at a time, while keeping one I-90 lane open.
    • The County Road 101 detour route is: Winona County Road 12 west at Dakota to Dakota Valley Drive east.

Summary of work

A resurfacing and bridge replacement project will occur on I-90 between Nodine and Dakota in Winona County. Construction is scheduled to begin May 4, 2026. Work is expected to be completed in November.

The following is the planned work on I-90:

I-90 Nodine Hills map
I-90 project map
  • Repave 5 miles of westbound and 4.7 miles of eastbound I-90.
  • Replace the westbound I-90 bridge over Winona Co. Rd. 101.
  • Replace approach panels and bridge barrier guardrail connections on the westbound I-90 bridge over southbound Hwy 61.
  • Improve safety by providing a slight banking of the right lane of northbound I-90 approaching the bridge over southbound Hwy 61.
  • Install new guardrail on the eastbound and westbound lanes and improve drainage.
  • Install a reinforcement and a synthetic liner to reduce sinkhole risks associated with Karst geology.
  • Clean and reestablish rock catchment areas.