Minnesota Department of Transportation

511 Travel Info

I-90/Hwy 52 interchange reconstruction

Olmsted County

Sign up for project email updates

About this project

Summary of work

I-90/Hwy 52 interchange project map
I-90/Hwy 52 interchange project map

Construction is scheduled 2024-2026 to make changes to the I-90/Hwy 52 interchange to improve safety and reduce delays. Work started July 15, 2024.

  • 2024: Construct temporary crossovers and begin new ramps and loops
  • 2025: Construct new eastbound I-90 bridge, flyover bridge over Hwy 52 and portion of new ramps and loops
  • 2026: Construct new westbound I-90 bridge and remaining portion of new ramps and loops

Improvements

A new feature, a flyover ramp, for southbound Hwy 52 to eastbound I-90, will solve several problems:

New ramps will reduce the run-off-the-road crashes:

  • Changing the angles will allow for better, more controlled entrance/exit
  • Lengthened accelerations lanes will also improve conditions

The bridge replacements will allow for:

  • Relocation of the bridge piers that block the view of on-coming traffic
  • Improved bridges that will last another 60 years or more

Proposed changes at interchange
Improvements at I-90 and Hwy 52 interchange

Traffic impacts

Check www.511mn.org or the free mobile app to see current traffic impacts. The below dates are subject to change.

I-90 off-ramps to Hwy 52 southbound are closed through November.

  • I-90 eastbound and westbound motorists exiting to Hwy 52 will be able to go north on Hwy 52.
  • I-90 eastbound and westbound motorists wanting to go south on Hwy 52 should take Exit 218 and travel north on Hwy 52, then exit to 50th Ave., turn left and exit to southbound Hwy 52.
  • I-90 motorists can also take Exit 224 near Eyota and go south on Olmsted Co. Rd. 7 to access Hwy 52 north of Chatfield.

A culvert will be installed under Hwy 52 at the I-90 interchange and that area will be closed and detoured. Work is tentatively scheduled for a few days late July to early August.

  • Motorists going north on Hwy 52 should go north on Co. Rd. 7, exit to westbound I-90 and take the Hwy 52 exit to access northbound Hwy 52.
  • Motorists going south on Hwy 52 should go south on Hwy 63, exit to eastbound I-90 and take the Hwy 52 exit to access southbound Hwy 52.

Traffic impacts in 2024 also include:

  • I-90 westbound and eastbound I-90 single lane traffic from two miles east of I-90/Hwy 52 interchange to two miles west of I-90/Hwy 52 interchange), scheduled July 15-Sept. 30
  • Hwy 52 lane closure in each direction between I-90 and 50th Ave. SE, scheduled July 16-18
  • Traffic shifts on northbound and southbound Hwy 52