Hwy 19/College Drive Reconstruction

Marshall

Orange barrels on a highway

Community Involvement

Promise to the public

MnDOT is committed to engaging with the community to clearly understand the concerns, priorities and aspirations of the community. We will listen to the community while considering improvements and we will provide feedback to the community on how input influences project decisions.

Timeline

  • Fall 2019: Collect feedback from community on vision and priorities (Feedback Summary PDF)
  • Summer 2020: Collect feedback from community on recommended intersection improvements
  • Fall 2020: Final intersection improvements (PDF)
  • Fall 2020: Collect feedback on project layout. To view the project layout click here
  • Summer 2021: Approval from city of Marshall on final project layout. - complete
  • Fall 2021: Begin detail design and right-of-way process
  • May 2025: Begin construction
  • Fall 2026: Complete construction