About this project
Summary of work
- Construct a single lane roundabout at the intersection of Hwy 212 and Morningside Ave. in Glencoe.
- Project includes adding a multi-use trail on all sides to connect to existing trails in the area.
Project update
Sep. 6, 2024
- Crews have paved the shoulders and bike trail, installed light poles and signs and placed the topsoil.
- Next up: seed alongside the roadway, and apply striping.
- Completed roundabout is anticipated to be open Sep. 13.
Traffic impacts
- Work will require a detour using CR 1, CR 3 and Hwy 22 (see map above).
Roundabouts
- Slow vehicle speeds and lower risk of serious and fatal crashes.
- Reduce traffic back-ups and improve traffic flow.
- Provide safe pedestrian and bike crossings.
- Learn about roundabouts at the MnDOT Roundabout website.