Hwy 23

Green Valley

About this project

MnDOT is planning to resurface two bridges on Hwy 23, north of Marshall crossing the Redwood River and Threemile Creek near Green Valley Map of Hwy 23 bridge repairs crossing the Redwood River and Threemile Creek north and south of green valley. Detour route for Hwy 23 routes vehicles onto Hwy 9 and Hwy 19

Summary of work

  • Resurface bridge decks
  • Replace approach panels
  • Replace guardrails

Traffic impacts

  • A detour is required for this project.
  • Traffic will be routed to Hwy 19 and CR 9.

Project updates

May 16, 2025

  • The project and detour began May 12.
  • Crews removed the low slumps off the existing decks and the guardrails.
  • The approach panels will be removed and deck repairs will begin next week.
  • Work will stop at noon on Friday prior to the holiday weekend.