Multi-lane Divided Roads
| MOBILE  15 minutes or less  | 
	        SHORT DURATION  1 hour or less  | 
	        SHORT TERM 12 hours or less  | 
	        INTERMEDIATE TERM 3 days or less  | 
          |
|---|---|---|---|---|
| Work vehicle parked on shoulder | 6 | 8 | ||
| Work on shoulder | 9 | 8 | ||
| Work off shoulder | 8 | |||
| Work off roadway | 10 | |||
| Shoulder or parking lane closure | 8 | |||
| Partial shoulder closure for Trailer Mounted Devices | 7 | |||
| Lane closures | ||||
| Mobile/short duration | 49, 50, 51 | |||
| Near intersection | 63 | 33, 64, 65, 66, 75 | ||
| Center lane | 56* | |||
| Left/right lane | 57, 58, 64, 65 | |||
| Turn lane | 33, 75 | |||
| Turn lane on dual turn lanes | 75 | |||
| Double lane | 51 | 59, 60 | ||
| Extended lane | 61 | |||
| Lane shift | 62 | |||
| Near ramp | 67, 68, 69 | |||
| Partial ramp closure | 70 | |||
| Ramp closure | 52, 53, 54 | 71, 72 | ||
| Closure at top of entrance ramp | 74 | |||
| Re-surfacing operation | 66 | |||
| Temporary road closure (15 minute intervals) | 55 | 73 | ||
| Temporary road closure | 32 | |||
| Sidewalk closure | 88, 89 | |||
| Bike lane closure | 87 | |||
| Crossroad and confirmation signing | 35 | |||
*NOTE: posted speed limit 35 mph or less only.