Payment process
State Aid agreement payment process
Federal aid agreement payment process
- Local Public Agency (LPA) prepares agreement payment request for eligible costs.
	      
- Sample bill (Word)
 - Backup documentation (see agreement for specific requirements)
	          
- Invoices
 - Timesheets, labor charges, equipment usage and rates, summary of charges
 - Cancelled checks (right-of-way agreements only)
 - Anything that documents the amount of funds spent for the project
 
 
 - LPA signs the coversheet and sends packet to District State Aid Engineer (DSAE).
 - DSAE reviews, signs, and dates coversheet. Forwards packet to SALT.
 - SALT reviews agreement and billing documentation.
	      
- Check date of authorization vs. date of billing and costs incurred
 - Check documentation submitted
 - Check type of work performed vs. project memo and agreement terms
 - Check charges, addition, etc. of billing
 
 - SALT requests payment on behalf of LPA from State Aid Finance.
 - State Aid Finance pays or requests clarification and then pays when proper justification is received.
 - If the request is a final payment, SALT will review and pay out the request amount minus any retainage to be held, per the agreement. This is typically 10 percent of the contract amount. 
	      
- SALT will then request a final audit which can take up to a couple of months.
 - Any agreement project that is less than $50,000 in total contract value is exempt from the final audit process.
 - When final audit process is complete, the retainage will be paid out in full.
 
 
Preaward audit
For Preliminary Engineering (PE) and Construction Engineering (CE) contracts which exceed $50,000, a preaward audit must be performed prior to the LPA signing the contract with the consultant providing services. See agreement overview process (PDF). Consult with Agreements Engineer. 
      