Washington St.—Brainerd

Hwy 210 from Baxter Dr. to Pine Shores Rd., Crow Wing County

Know before you go: check 511mn.org

Current impacts

Prepare work zone

Crews prepare work zone. Select map to enlarge (PNG)

Hwy 210 - Pine Shores Rd. to Fifth Ave.

  • Be alert to lane shifts, shoulder closures and slow moving trucks entering/exiting work areas:
  • Local access open along Hwy 210; however, expect changes, follow signs:
    • Hwy 25 access open to/from 10th Ave. NE
  • Current work zone map (PNG)

Note: CenterPoint Energy is closing city streets in east Brainerd to complete underground gas line work. This includes periodic lane closures on Hwy 210 near SE 13th St./Gillis Ave.

Upcoming impacts

Construct mall segment

Hwy 210 - 10th Ave. NE to Fifth Ave. NE

Detour mall segment
Mall segment detour map. Select map to enlarge.
Week of May 11-18

Crews will close Hwy 210 and begin building the two new roundabouts in the mall segment (PNG).

Motorists

  • Hwy 210 will be one lane in each direction, 24/7, and detoured around the closed work area in east Brainerd
    • Use Tenth Ave. NE and Hwy 25. Detour/work zone map (PNG)
    • A temporary signal will operate at Tenth Ave. NE and Hwy 25.
    • Expect delays; consider alternate routes or traveling during off-peak hours.
    • Brainerd is open. Local access to the mall area/Mill Ave. via Fourth Ave. NE and E St. NE
  • Truck detour: Co. Rd. 3 closed at Hwy 210 (PNG) Follow road signs to/from Co. Rd. 3, Hwy 210, Hwy 25. Turn radius tight, please use truck detour for semi-trailer/longer vehicles, including recreational vehicles pulling campers or long trailers.

Pedestrians

  • Sidewalk closures, follow detour signs

About this project

MnDOT will reconstruct and improve the Washington St. (Hwy 210) through Brainerd from Baxter Dr. to Pine Shores Rd. in 2026 and 2027.

Hwy 210

  • Reconstruct (mall, railyard, downtown, bridge segments) or resurface (east and west segments) the road
  • Reconstruct curbs, gutters, raised medians and storm sewers
  • Update signal systems
  • Remove signal systems at Mill Ave. and 4th Ave. NE
  • Realign and improve access at the Hwy 210 and Hwy 25/Mill Ave., includes two roundabouts
  • Upgrade city utilities beneath the road
  • Upgrade pedestrian sidewalks and approaches and reconstruct/connect the Cuyuna Lakes Trail
  • Update the Mississippi River bridge
Project location map and general segments. Select image to enlarge

Hwy 210 segments

2026 work
  • East— 10th Ave. NE to Pine Shores Rd.
  • Mall—5th Ave. E to 10th Ave. NE
  • Railyard —Kingwood St. to 5th Ave.
2027 work
  • Downtown — E River Rd./N 1st St. to Kingwood St.
  • Bridge— 4th St. NW to east of the Mississippi River at E River Rd./N 1st St.
  • West — Baxter Dr. to 4th St. NW

Work segments subject to change once more is known. More details to become available closer to construction.